Skip to main content

SE 384th Street Culvert Replacement Project

Construction anticipated in summer 2025

The culvert replacement project is located on SE 384th Street west of 176th Ave SE near Auburn, WA. Crews will remove a four-foot-wide concrete pipe that is too small to handle water during storms. A new much larger concrete box culvert will be installed in its place and will prevent flooding on private property and on nearby roads.

Status update

Spring 2025

Construction requires a full road closure, and the closure is scheduled to last eight weeks. It is anticipated to begin in August 2025. Please check this website and sign up to receive email/text notifications about the project at Road Alerts

Project overview

During heavy rains, the culvert under SE 384th Street west of 176th Avenue SE is too small to handle the water. This can lead to flooding upstream on roads as far as 176th Avenue SE along with flooding on nearby private property. The current four-foot-diameter concrete pipe will be replaced with a much larger concrete box culvert. This work will require an eight-week road closure.

Crews will dig a large pit in the road to remove the old 48-inch-wide concrete pipe. Then, they’ll prepare the ground to install a new culvert. They’ll use a large crane to put the bottom and sides of the new culvert in the ground. The inside of the new culvert will look like a streambed with natural materials. After that, crews will put the lid of the culvert in place with the crane and rebuild and pave the road.

While there are currently additional downstream barriers to fish, once those are removed this culvert is designed to be fish passable and will allow salmon, trout, and other fish to swim farther up Charlie Jones Creek to their spawning grounds.

24/7 Road Helpline contact information

24/7 Road Helpline

Report road maintenance and safety issues in unincorporated King County 24 hours a day at 206-477-8100 or 1-800-527-6237.

Project location map

 

This project is located on SE 384th Street just north of the Muckleshoot Reservation and to the southeast of Auburn, WA. 

What to expect during construction

SE 384th Street will be closed for eight weeks during construction. The road is too narrow—there isn’t enough space for the big construction crane and other equipment to keep even one lane open for traffic. All vehicles, including emergency vehicles such as fire trucks, bicycles, and pedestrians must use the detour route during the closure.

People living nearby may notice noise and smells from saw cutting, jackhammers, excavators, generators, and pumps. There will also be trucks hauling materials and large cranes in the roadway. 

After the new culvert is open to traffic, crews will do some low-impact restoration work, like adding native plants and site cleanup. 

Detour route

 

During the eight-week road closure on SE 384th Street for culvert construction, travelers will use the marked detour route on SR 164, 180th Ave SE, and SE 400th St. 

Budget and funding sources

The estimated budget for this project is $2 million, and the funding will be provided by County sources and a grant from the County Road Administration Board.  

Project timeline

  • Design complete: Spring 2025
  • Construction work: late August 2025 
  • Substantial construction complete: September 2025 
 

Frequently asked questions

No. There will be an open construction pit in the road during construction. It is not safe for any vehicles (including emergency vehicles), bicycles, or foot traffic to use the road when it is closed for this kind of construction work. We are coordinating with emergency responders to minimize any additional response time when the road is closed.
No. The work zone will be a deep open pit and will be unsafe for people who are not crewmembers.
The average daily use of SE 384th Street is approximately 1,200 vehicles a day. 

SE 384th Street is too narrow to have enough room for a large construction crane and other necessary equipment while safely maintaining even a single lane of alternating traffic through the work area. There are no shoulders to store equipment. 

It will take approximately eight weeks to remove the old pipe and install the new box culvert under the road. 


The existing concrete pipe is 64 feet long and 48 inches (4-feet) in diameter.
The new box culvert will be 18-feet-wide, 9.3-feet high and 45-feet long.

A fish passage barrier is anything that makes it very difficult for fish to swim upstream or downstream. 

Most fish barriers in unincorporated King County are round pipes (culverts) that channel streams and water underneath the road. Many of these culverts were installed between 30 and 100 years ago. These older culverts allow water to flow but are so narrow and steep that they prevent fish from swimming through them.

The current concrete pipe is a fish passage barrier in Charlie Jones Creek, however, there are additional barriers downstream that will need to be removed before fish will be able to return to and from this location. Once the pipe is replaced under SE 384th Street it will no longer be a fish passage barrier and will allow passage if they return at a future date. 

Once all fish passage barriers are removed the following species have the potential to return to Charlie Jones Creek: 

  • Winter steelhead
  • Pink 
  • Coho
  • Fall chum
  • Fall chinook
  • Odd year pink
  • Coastal cutthroat trout
  • Bull trout
 
Yes. Up to four mature trees and a mix of smaller trees and shrubs will be removed to install the new box culvert. As a part of the project, the County will replant the area to restore the site. 
We will update this website with more information leading up to the start of construction. Sign up for Road Alerts to receive an email or SMS text message prior to construction. You are welcome to contact Amy Bresslour with any questions or concerns. 

Photos

The current four-foot diameter pipe will be removed and replaced with a much larger concrete box culvert. The new pipe will be large enough to handle water in the rainy season and during winter storms. 

 

This concrete box culvert on SE 380th Place was built in 2022 and is a simular design to the new culvert on SE 384th Street. Both large structures are filled with gravel and large rocks along with natural materials to mimic a streambed. 

expand_less