Land use inspections
Important Information
Before You Begin Construction
- Keep approved plans and permits posted on‑site at all times. Maintaining these records is the responsibility of the applicant and/or contractor.
- All projects require a pre-construction conference before any land clearing or grading.
- A Notice of Construction Activity sign may be required for subdivisions, commercial permits, or grading permits subject to SEPA. An Erosion Control Supervisor sign must be posted per the Surface Water Design Manual.
Drainage facility liability insurance
King County Code Title 9.04.100 requires the applicant to post liability insurance that names King County as an additional insured to protect King County from liability.
Pre‑Construction Conference
A pre-construction conference is required before any land clearing or grading on a site that requires permit approval. This includes:
- Subdivisions and short plats
- Clearing and grading permits
- Right‑of‑way use permits
- Some commercial and large residential projects
To request a conference, contact your assigned inspector directly to schedule inspections. If you do not know who your assigned inspector(s) are, contact King County Permitting Customer Service at 206‑296‑6600 for assistance.
Right-of-way use permit inspection
A right-of-way use permit (limited or extended) is required for any private improvement or use of a King County right-of-way.
Inspection Overview
This section gives an overview of the inspections your project may require and helps you understand who performs them and how they fit into the overall permitting and construction process.
Types of Inspections
Land Use / Site Inspections
A land use / site inspector will be assigned to your project after permit approval and the required preconstruction conference.
- Contact your assigned inspector directly to schedule inspections. Land use inspections cannot be scheduled online or using the automated phone system used for building permits.
- Refer to the County’s required lead times for each activity (typically 1–3 business days; longer for final inspections).
- Please reference your permit number (for example, LUIS26‑0001) with all inspection requests.
Critical Areas Inspections
- Projects involving critical areas or critical area buffers may require additional inspections.
- These inspections must be scheduled directly with the Permitting Division Ecologist and/or Geologist.
Coordination With Other Inspectors
Permitting Land Use Inspectors serve as the primary point of contact for your project; however, some inspection types require coordination with Roads Division and/or Water and Land Resources Division (WLRD) inspectors. Your assigned Land Use Inspector will help facilitate this coordination as needed.
How to Schedule Inspections
Scheduling
- Contact your assigned inspector directly to schedule inspections.
- Land use inspections cannot be scheduled online or using the automated phone system used for building permits.
- Refer to the County’s required lead times for each activity (typically 1–3 business days; longer for final inspections).
- Please reference your permit number (for example, LUIS26‑0001) with all inspection requests.
If You Don’t Know Who Your Inspector Is
- Contact King County Permitting Customer Service at 206‑296‑6600 for assistance.
- Customer service can confirm your assigned inspector(s), help you understand inspection requirements, and direct you to the correct reviewer for technical inspections.
Contact a land use inspector
Land use / site inspections must be made by calling an inspector directly - they cannot be scheduled online or through the automated phone system.
Inspectors are out doing inspections most of the day, so they can’t respond immediately to calls. Please leave a message or send email.
King County Building Official / Site Inspection Supervisor:
206-848-0368
Site inspectors:
206-477-7075
206-477-3410
Required Lead Times for Land Use Inspections
The following inspections are required under the King County Road Design and Construction Standards. Before beginning any applicable activity, you must schedule the corresponding inspection and follow the required lead time.
| Inspection Type | Required Lead Time |
|---|---|
| Preconstruction meeting | 3 working days |
| Clearing and temporary erosion control | 1 working day |
| Utility and storm drainage installation | 1 working day |
| Backfill and compaction | 1 working day |
| Subgrade completion | 1 working day |
| Curb and sidewalk forming | 1 working day |
| Crushed surfacing placement | 1 working day |
| Paving | 3 working days |
| Structural work | 3 working days |
| Final punch list inspection | 15 working days |
References and Resources
King County Road Design and Construction Standards
A comprehensive set of design and construction requirements for public roadways in King County that supports consistent, compliant review during land use inspections.
King County Surface Water Design Manual
Requirements and standards for designing surface and stormwater management systems in King County to mitigate the impacts of new development and redevelopment on natural and existing man-made drainage systems.
Commercial Best Management Practice Activity
Provides guidance on pollution prevention Best Management Practices (BMPs) for commercial and multifamily properties in King County to help reduce stormwater contamination during site activities.
Residential Best Management Practice Activity Sheets
Provides Best Management Practice (BMP) guidance specifically for residential properties in King County to reduce stormwater pollution and support compliance with site development and land use inspections.
Stormwater Pollution Prevention Manual Information Sheets
Provides detailed stormwater pollution prevention information sheets that support residential and commercial Best Management Practices (BMPs) in King County by explaining specific practices referenced during site and land use inspections.